How long do the steps take? No two jobs are the same, but here are some reasonable estimates of what will be required for each stage. Do keep in mind, though, that even the best organized job will, occasionally, have quiet days when work is on hold because of scheduling conflicts, delays in deliveries, and the rest.

STEP / TASK

TIME REQUIRED

1.

Surveyor staking foundation location

V2 day

2.

Excavation and, if necessary, clearing and tree removal

1-2 days

3.

Footing and foundation work, including time for curing concrete, installing drain tile, waterproofing, back filling, etc.

2-3 weeks

4.

Framing

1-3 weeks

5.

Roofing and flashing work, chimney installation

1-2 weeks

6.

Window, exterior door installation, siding, trim

2-4 weeks

7.

Electrical, plumbing, other rough-ins (overlaps with Step 6) and insulation

1-2 weeks

8.

Walls and ceilings

2 weeks

9.

Finish work: interior trim, doors, floors, cabinets, painting, set fixtures, etc.

2-8 weeks

10.

Punch list, final inspection, etc.

1 week



Comments:

  1. Wulf

    Just cute !!

  2. Fergusson

    And the Swiss, and the reaper, and in general, fucked up. The most amazing thing about pop singers is that they sing with their mouths in the same way ... Fresh food, but it is hard to fight What you warm on your chest, it will sizzle all your life. It is very easy to make a woman happy. Only expensive. Nothing warms the soul like cold beer ...

  3. Zachary

    Congratulations, you just had a great thought.

  4. Lambert

    wonderfully, it's valuable information

  5. Merla

    Sorry to interfere, but could you please describe in a little more detail.



Write a message